Northern Territory

coin-icon

Power and Water Corporation

calendar-icon

June 2017 - December 2018

coin-icon

$14.5 million

stopwatch-icon

Complete


Scope

The scope of work included:

  • bulk earthworks
  • piling works
  • construction of reinforced concrete inlet structure complete with pump well and elevated inlet structure
  • construction of access roads
  • supply and installation of mechanical equipment including lift pumps, band screens, grit classifier system, recycled effluent water filter system and associated above and below ground pipework including recycled effluent and glass reinforced pipe
  • supply and installation of valves and instrumentation
  • supply and installation of new electrical switch room and associated high voltage and low voltage works complete with SCADA control
  • installation of designated odour control system, complete with biotrical filter, caron expansion and odour covers
  • repair works to existing assets
  • testing and commissioning of the plant.

Outcomes

BMD Constructions undertook several design optimisations on the project including the removal of a proposed secondary pump station in favour of overland drainage, and the comprehensive consolidation of all mechanical equipment. Both of these initiatives led to key savings for the client.

Further upgrades and maintenance works at the plant were scheduled to commence following the completion of BMD Constructions’ project. As a result of the project team’s collaborative relationship with the client, BMD managed the tight interface to allow for additional works to be carried out by the client without disruption.

Safety was of the upmost priority for the project team, with 65,000 hours worked over the 18 month project duration with no lost time injuries. BMD developed a safe approach to excavate next to the existing treatment ponds to allow for the construction and installation of the inlet pump station. During this operation seepage from the existing ponds was managed to maintain the safety of the excavation.

As a result of BMD’s focus on local industry participation, 90% of the work was delivered locally by over 15 Northern Territory contractors and 85% of material supplied for the project was sourced locally by over 18 Northern Territory suppliers.