Scope

The scope of work included:

  • stripping of 9100m2 topsoil and existing turf
  • 700m3 of earthworks
  • installation of 235m2 of retaining walls
  • installation of 200 metres of a new spectator fence, installed at both ends of the playing field
  • 9100m2 of turfing and grass seeding
  • removal and installation of new irrigation
  • removal and relocation of existing goal posts, scoreboard and lighting.

Outcomes

BMD Urban had a very strict project timeframe in order to complete works in the rugby league off-season, prior to the commencement of pre-season training. Through effective planning and a collaborative approach, the project was completed on time and without incident.